 Permit
 Status
 
Commercial Vehicle/Overdimension Restrictions.
VERMONT
Permit Status - Interstate 89
Interstate 89 southbound: at Exit 8: Montpelier State Highway
left lane closed, traffic restrictions in force because of bridge maintenance work — for the next three weeks
Comment: Bridge work is being done on I-89 just north of Exit 8 . One lane will be closed in the construction area with a lane width of 12 feet. The speed limit in the construction area will be reduced to 50 MPH. Drive with caution.

last updated September 3
 
Permit Status - Interstate 91
Interstate 91 in both directions: at Exit 17: US 302
road construction, roadway reduced to one lane, speed restrictions in force because the road is being repaved — for the next month
Comment: Paving work continues at Exit 17 in both directions. Daily lane closures can be expected. Speed limits are reduced to 55 MPH.

last updated August 10
 
Permit Status - Interstate 91
Interstate 91 northbound: from after Exit 17: US 302 to before Exit 18: Barnet State Highway
bridge maintenance operations, traffic restrictions in force — until October 15
Comment: Bridges number 67N & 69N in Bradford-Ryegate area on I-91 will undergo membrane replacement. There will be one lane traffic in the construction area at different times with a minimum lane width of 15 feet. A speed limit of 50MPH will be enforced in the work zone.

last updated March 26
 
Permit Status - Interstate 91
Interstate 91 northbound: from after Exit 18: Barnet State Highway to before Exit 19: I-93
bridge maintenance operations, traffic restrictions in force — until October 15
Comment: Bridge numbers 76N, 77N and 78N in the Barnet area will undergo membrane replacement. There will be one lane traffic in the construction area at different times with a minimum lane width of 15 feet. A speed lilmit of 50 MPH will be enforced in the work zone.

last updated March 26
 
Permit Status - Interstate 91
Interstate 91 in both directions: from Exit 20: US 5 to before Exit 25: VT 16
bridge maintenance operations, traffic restrictions in force, lane closed — until October 1
Comment: This project involves membrane replacement of a total of 12 bridges over the course of several months. Multiple work zones will be set up with lane closures that will alternate as work progresses. A roadway width of 14 feet can be expected through the work zones as well as a reduced speed limit of 50 MPH.

last updated March 29
 
Permit Status - Interstate 91
Interstate 91 southbound: from after Exit 24: VT 122 to before Exit 26: US 5
construction work, roadway reduced to one lane, speed restrictions in force because the road is being repaved — until today at about 6:00 PM EDT
Comment: Hours of operation are expected to be 6AM to 8PM 7 days a week.

last updated July 28
 
Permit Status - US 2
US 2: at I-89
height limit in effect — clearing this month
Comment: Vertical Clearance will be reduced on Route 2 under bridge #56 at I-89 Exit 11 in Richmond to allow for bridge maintanance. Clearance will be reduced from 18 feet to 14 feet six inches. The speed limit will be reduced to 35 MPH in the work zone.

last updated July 29
 
Permit Status - US 7
US 7 in both directions: from Florence Road to Mcconnell Road
major road construction, short delays, traffic restrictions in force — for the next three weeks

last updated August 30
 
Permit Status - Vermont 11
Vermont 11: at Andover Road
speed restrictions in force because of bridge maintenance work —

last updated July 15
 
Permit Status - Vermont 12
Vermont 12: from North Calais Road to Elmore Pond Road
construction work, single line traffic - alternating directions, delays, speed restrictions in force because the road is being repaved — until October 15
Comment: Project length is approximatly 8 miles from Hancock Brook Road in Worcester north to Lacasse Road in Elmore. Expect multiple work zones. The road surface is rough in places with low shoulders. Vehicles, espicially motorcycles should use extreme caution.

last updated July 9
 
Permit Status - Vermont 14
Vermont 14: from US 2 to VT 214
construction work, traffic restrictions in force due to bridge construction work — until October 1
Comment: This project will resume on 04/28/10 and involves the construction of a new bridge on Route 14 just north of E. Montpelier. A 30 MPH speed limit is advised through the detour with a 40 MPH Limit in the construction zone. The lane width narrows to 11 feet.

last updated April 26
 
Permit Status - Vermont 64
Vermont 64 northbound: at I-89
trucker info -- trucks are recommended to avoid the area —
Comment: There are steep grades on Route 64 from I-89 to Williamstown. It's recommended that large trucks use Exit 6 for Williamstown.

last updated October 28
 
Permit Status - Vermont 65
Vermont 65: after Ridge Road
no through traffic
Comment: The "Floating Bridge" in Brookfield is closed for the winter season and will remain closed to all but pedestrian traffic for the foreseeable future.

last updated December 22
 
Permit Status - Vermont 125
Vermont 125: from VT 30 to after Lincoln Road
construction work, delays, speed restrictions in force because the road is being repaved — for the next month

last updated August 9
no through traffic on Vermont 65 after Ridge Road last updated December 22 construction work, roadway reduced to one lane, speed restrictions in force on Interstate 91 southbound from after Exit 24: VT 122 to before Exit 26: US 5 because the road is being repaved — until today at about 6:00 PM EDT last updated July 28 road construction, roadway reduced to one lane, speed restrictions in force on Interstate 91 in both directions at Exit 17: US 302 because the road is being repaved — for the next month last updated August 10 construction work, delays, speed restrictions in force on Vermont 125 from VT 30 to after Lincoln Road because the road is being repaved — for the next month last updated August 9 bridge maintenance operations, traffic restrictions in force, lane closed on Interstate 91 in both directions from Exit 20: US 5 to before Exit 25: VT 16 — until October 1 last updated March 29 construction work, single line traffic - alternating directions, delays, speed restrictions in force on Vermont 12 from North Calais Road to Elmore Pond Road because the road is being repaved — until October 15 last updated July 9 major road construction, short delays, traffic restrictions in force on US 7 in both directions from Florence Road to Mcconnell Road — for the next three weeks last updated August 30 trucker info on Vermont 64 northbound at I-89 -- trucks are recommended to avoid the area — last updated October 28 bridge maintenance operations, traffic restrictions in force on Interstate 91 northbound from after Exit 18: Barnet State Highway to before Exit 19: I-93 — until October 15 last updated March 26 height limit in effect on US 2 at I-89 — clearing this month last updated July 29 bridge maintenance operations, traffic restrictions in force on Interstate 91 northbound from after Exit 17: US 302 to before Exit 18: Barnet State Highway — until October 15 last updated March 26 speed restrictions in force on Vermont 11 at Andover Road because of bridge maintenance work — last updated July 15 construction work, traffic restrictions in force on Vermont 14 from US 2 to VT 214 due to bridge construction work — until October 1 last updated April 26 left lane closed, traffic restrictions in force on Interstate 89 southbound at Exit 8: Montpelier State Highway because of bridge maintenance work — for the next three weeks last updated September 3